San Bruno Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Bruno
Zip Code
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
 
County/State Route San Mateo ct
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$30,000 $-3,273 $26,727
Non-bond Funding
State/Federal*
$10,000 $25,871 $35,871
Local**
$125,000 $-40,548 $84,452
 
Total**** $165,000 $-17,950 $147,050

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$14,250 $0 $14,250 $13,439 $13,439 $811
Design(PS&E)
$25,700 $0 $25,700 $11,394 $11,394 $14,306
Right of Way
$2,600 $0 $2,600 $1,343 $1,343 $1,257
Construction
$122,450 $-17,950 $104,500 $104,839 $104,839 $-339
 
Total* $165,000 $-17,950 $147,050 $131,015 $131,015 $16,035

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2004 

12/31/2008 
 

 
06/01/2004 

01/02/2009 
100   

10/20/2009 


-10 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/02/2009 

12/01/2009 
 

 
02/02/2009 

12/01/2009 
100   

05/18/2010 


-6 
Begin Right of Way Phase

End Right of Way Phase
10/01/2008 

06/30/2010 
 

 
10/01/2008 

06/30/2010 
100   

03/11/2010 


Begin Construction Phase

End Construction Phase
07/01/2010 

10/31/2012 
03/28/2012 

03/28/2012 
07/01/2010 

10/31/2012 
99   

 


Begin Closeout Phase

End Closeout Phase
11/01/2012 

05/01/2013 
 

 
11/01/2012 

05/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
$30,000,000
Current Approved:
$26,727,000
Actual Expenditures:
$26,727,000

 

Status as of December 31, 2023.