Betty Drive Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City
Zip Code
 
Senate District
16
Assembly District 30
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  1320      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$12,175 $-7,320 $4,855
Non-bond Funding
Local**
$15,900 $-6,461 $9,439
 
Total**** $28,075 $-13,781 $14,294

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$343 $-127 $216 $216 $216 $0
Design(PS&E)
$1,336 $-239 $1,097 $1,097 $1,097 $0
Right of Way
$546 $1,859 $2,405 $2,405 $2,405 $0
Construction
$25,850 $-15,274 $10,576 $10,606 $10,606 $-30
 
Total* $28,075 $-13,781 $14,294 $14,324 $14,324 $-30

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/09/2008 

05/29/2009 
 

 
06/09/2008 

05/29/2009 
100   

05/25/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/02/2009 

03/01/2010 
 

 
02/02/2009 

03/01/2010 
100   

09/28/2010 


-7 
Begin Right of Way Phase

End Right of Way Phase
08/31/2009 

05/29/2010 
 

 
08/31/2009 

05/29/2010 
100   

11/02/2010 


-5 
Begin Construction Phase

End Construction Phase
06/01/2010 

06/06/2011 
03/28/2012 

03/28/2012 
12/20/2010 

06/01/2011 
100   

12/30/2012 


-19 
Begin Closeout Phase

End Closeout Phase
06/06/2011 

07/11/2011 
 

 
06/06/2011 

07/11/2011 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 1320

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

Click to view the Final Audit Report

 

Status as of December 31, 2023.