Bardsley Avenue Grade Separation |
Description: Construct a Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | |
Zip Code | |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 21 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 14 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | (916) 654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$7,156 | $-129 | $7,027 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$9,075 | $637 | $9,712 | ||||
Private*** |
$1,143 | $487 | $1,630 | ||||
Total**** | $17,374 | $995 | $18,369 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$171 | $93 | $264 | $299 | $299 | $-35 | |
Design(PS&E) |
$1,776 | $-1 | $1,775 | $1,639 | $1,639 | $136 | |
Right of Way |
$1,600 | $95 | $1,695 | $1,559 | $1,559 | $136 | |
Construction |
$13,827 | $808 | $14,635 | $13,234 | $13,234 | $1,401 | |
Total* | $17,374 | $995 | $18,369 | $16,731 | $16,731 | $1,638 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2008 12/01/2008 |
09/07/2010 09/07/2010 |
06/01/2008 12/01/2008 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 04/01/2009 |
01/08/2013 |
01/01/2009 04/30/2012 |
100 | 11/30/2010 |
0 17 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2009 04/01/2010 |
01/08/2013 |
04/01/2009 04/30/2012 |
100 | 10/31/2010 |
0 18 |
Begin Construction Phase
End Construction Phase |
06/01/2010 06/01/2012 |
01/08/2013 01/08/2013 |
11/15/2012 02/28/2015 |
100 | 10/31/2012 |
0 28 |
Begin Closeout Phase
End Closeout Phase |
07/01/2012 09/01/2012 |
01/08/2013 08/31/2016 |
04/01/2014 05/31/2014 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 14 |
Bond Funding Cost | |
---|---|
Adopted: |
$7,156,000 |
Current Approved: |
$7,156,000 |
Actual Expenditures: |
$7,027,000 |
Status as of December 31, 2023.