Bardsley Avenue Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City
Zip Code
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  14      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$7,156 $-129 $7,027
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$9,075 $637 $9,712
Private***
$1,143 $487 $1,630
 
Total**** $17,374 $995 $18,369

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$171 $93 $264 $299 $299 $-35
Design(PS&E)
$1,776 $-1 $1,775 $1,639 $1,639 $136
Right of Way
$1,600 $95 $1,695 $1,559 $1,559 $136
Construction
$13,827 $808 $14,635 $13,234 $13,234 $1,401
 
Total* $17,374 $995 $18,369 $16,731 $16,731 $1,638

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2008 

12/01/2008 
09/07/2010 

09/07/2010 
06/01/2008 

12/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

04/01/2009 
 

01/08/2013 
01/01/2009 

04/30/2012 
100   

11/30/2010 


17 
Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

04/01/2010 
 

01/08/2013 
04/01/2009 

04/30/2012 
100   

10/31/2010 


18 
Begin Construction Phase

End Construction Phase
06/01/2010 

06/01/2012 
01/08/2013 

01/08/2013 
11/15/2012 

02/28/2015 
100   

10/31/2012 


28 
Begin Closeout Phase

End Closeout Phase
07/01/2012 

09/01/2012 
01/08/2013 

08/31/2016 
04/01/2014 

05/31/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 14

Bond Funding Cost
Adopted:
$7,156,000
Current Approved:
$7,156,000
Actual Expenditures:
$7,027,000

 

Status as of December 31, 2023.