Cartmill Avenue Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Tulare
Zip Code
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  25    25  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$11,293 $-1,242 $10,051
Non-bond Funding
Local**
$11,467 $4,048 $15,515
 
Total**** $22,760 $2,806 $25,566

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$171 $0 $171 $472 $472 $-301
Design(PS&E)
$1,896 $535 $2,431 $2,138 $2,138 $293
Right of Way
$1,400 $4,850 $6,250 $4,585 $4,585 $1,665
Construction
$19,293 $-2,579 $16,714 $13,404 $13,404 $3,310
 
Total* $22,760 $2,806 $25,566 $20,599 $20,599 $4,967

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2008 

12/31/2008 
 

 
06/01/2008 

12/31/2008 
100   

11/30/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

04/01/2010 
 

 
01/01/2009 

04/30/2010 
100   

08/15/2010 


-4 
Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

04/01/2010 
 

 
04/01/2009 

04/30/2010 
100   

06/22/2010 


-2 
Begin Construction Phase

End Construction Phase
06/01/2010 

11/01/2011 
03/28/2012 

03/28/2012 
12/01/2010 

05/31/2012 
100   

01/03/2013 


-7 
Begin Closeout Phase

End Closeout Phase
12/01/2011 

02/01/2012 
 

 
12/01/2011 

02/01/2012 
50   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 25 25

Bond Funding Cost
Adopted:
$11,293,000
Current Approved:
$10,743,000
Actual Expenditures:
$10,160,927

Click to view the Final Audit Report

 

Status as of December 31, 2023.