Grant Line Road Grade Separation with UPPR

Description: Construct a grade separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elk Grove
Zip Code
 
Senate District
01
Assembly District 15
Congressional District 03
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Elk Grove Gary Grunwald 9164782236   ggrunwald@elkgrovecity.org
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,000 $-1,844 $3,156
Non-bond Funding
Local**
$24,775 $0 $24,775
Private***
$600 $0 $600
 
Total**** $30,375 $-1,844 $28,531

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,122 $0 $2,122 $2,122 $2,122 $0
Design(PS&E)
$2,800 $0 $2,800 $2,800 $2,800 $0
Right of Way
$4,733 $0 $4,733 $4,733 $4,733 $0
Construction
$20,720 $-1,844 $18,876 $6,802 $17,469 $1,407
 
Total* $30,375 $-1,844 $28,531 $16,457 $16,457 $12,074

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2004 

02/01/2011 
12/06/2012 

12/06/2012 
12/01/2004 

02/01/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2009 

06/01/2012 
12/06/2012 

12/06/2012 
12/01/2009 

06/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
04/01/2010 

12/01/2012 
12/06/2012 

12/06/2012 
04/01/2010 

12/01/2012 
100   

 


Begin Construction Phase

End Construction Phase
02/27/2013 

12/01/2014 
12/06/2012 

12/06/2012 
02/27/2013 

04/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2015 

06/01/2015 
12/06/2012 

08/01/2016 
09/01/2015 

10/01/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
$5,000,000
Current Approved:
$5,000,000
Actual Expenditures:
$3,156,000

 

Status as of December 31, 2023.