Lathrop Road

Description: Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Lathrop
Zip Code
 
Senate District
05
Assembly District 17
Congressional District 17, 18
 
Caltrans District
10
 
 
County/State Route San Joaquin 10
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Lathrop Mary Grace Houlihan 2099417453   mhoulihan@ci.lathrop.ca.us
 
Corridor System Management Plan
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,000 $0 $5,000
Non-bond Funding
Local**
$11,855 $0 $11,855
 
Total**** $16,855 $0 $16,855

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $400 $400 $-400
Design(PS&E)
$200 $0 $200 $1,064 $1,064 $-864
Right of Way
$400 $0 $400 $1,968 $1,968 $-1,568
Construction
$16,255 $0 $16,255 $14,530 $19,530 $-3,275
 
Total* $16,855 $0 $16,855 $17,962 $22,962 $-6,107

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2008 

10/01/2009 
 

 
01/01/2008 

10/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2011 

10/31/2012 
 

 
02/01/2011 

10/31/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2011 

10/31/2012 
 

 
02/01/2011 

10/31/2012 
100   

 


Begin Construction Phase

End Construction Phase
01/01/2013 

10/01/2015 
 

 
08/05/2013 

10/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2015 

01/01/2016 
 

09/01/2016 
10/01/2015 

01/01/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
$5,000,000
Current Approved:
$5,000,000
Actual Expenditures:
$5,000,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.