Santa Fe Trail

Description: Grade Separation Project

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Tulare
Zip Code 93274
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$3,931 $0 $3,931
Non-bond Funding
Local**
$3,447 $-15 $3,432
 
Total**** $7,378 $-15 $7,363

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$61 $0 $61 $0 $0 $61
Design(PS&E)
$765 $0 $765 $0 $0 $765
Right of Way
$15 $0 $15 $0 $0 $15
Construction
$6,537 $-15 $6,522 $7,131 $14,262 $-7,740
 
Total* $7,378 $-15 $7,363 $7,131 $14,262 $-6,899

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/30/2012 

01/31/2013 
 

 
06/30/2012 

01/31/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2013 

12/31/2013 
 

 
03/01/2013 

12/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2013 

11/30/2013 
 

 
03/01/2013 

11/30/2013 
 

 


Begin Construction Phase

End Construction Phase
02/01/2014 

12/31/2014 
 

 
02/01/2014 

12/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

02/28/2015 
08/01/2016 

12/31/2016 
01/01/2015 

02/28/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
$3,381,000
Current Approved:
$3,931,000
Actual Expenditures:
$3,931,000

 

Status as of December 31, 2023.