Durfee Avenue Grade Separation

Description: Durfee Avenue Grade Separation in the City of Pico Rivera

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Pico Rivera
Zip Code 90662
 
Senate District
32
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
 
County/State Route Los Angeles N/A
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$0 $0 $0
HRCSA
$2,706 $0 $2,706
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$78,381 $10,056 $88,437
 
Total**** $81,087 $10,056 $91,143

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$8,738 $308 $9,046 $9,752 $9,752 $-706
Right of Way
$27,771 $4,853 $32,624 $28,689 $28,689 $3,935
Construction
$44,578 $4,895 $49,473 $55,847 $55,847 $-6,374
 
Total* $81,087 $10,056 $91,143 $94,288 $94,288 $-3,145

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
12/31/2017 

12/31/2017 
10/01/2012 

11/30/2017 
100  10/10/2012 

05/01/2018 


-5 
Begin Right of Way Phase

End Right of Way Phase
 

 
12/31/2017 

12/31/2017 
12/01/2014 

10/31/2017 
99  04/29/2013 

09/30/2022 
19 

-60 
Begin Construction Phase

End Construction Phase
 

 
12/31/2017 

12/31/2017 
04/01/2018 

10/31/2020 
99  06/10/2019 

07/31/2023 
-14 

-33 
Begin Closeout Phase

End Closeout Phase
 

 
12/31/2017 

12/31/2017 
11/01/2020 

07/31/2021 
08/01/2023 

12/31/2023 
-33 

-29 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.