BNSF Grade Separation at 7th Standard Rd/Santa Fe Way

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City
Zip Code
 
Senate District
32
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  4    4  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$9,926 $-2,882 $7,044
Non-bond Funding
State/Federal*
$6,500 $-630 $5,870
Local**
$11,089 $-3,037 $8,052
Private***
$1,338 $-376 $962
 
Total**** $28,853 $-6,925 $21,928

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,120 $-1,272 $848 $848 $848 $0
Design(PS&E)
$1,880 $-155 $1,725 $1,465 $1,465 $260
Right of Way
$1,500 $2,650 $4,150 $3,796 $3,796 $354
Construction
$23,353 $-8,148 $15,205 $13,960 $13,960 $1,245
 
Total* $28,853 $-6,925 $21,928 $20,069 $20,069 $1,859

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2002 

05/19/2006 
 

 
05/01/2002 

05/19/2006 
100   

05/19/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2006 

06/01/2008 
 

 
11/01/2006 

06/01/2008 
100   

11/01/2008 


-5 
Begin Right of Way Phase

End Right of Way Phase
11/01/2006 

09/01/2008 
 

 
11/01/2006 

09/01/2008 
100   

06/15/2011 


-34 
Begin Construction Phase

End Construction Phase
04/01/2009 

04/01/2011 
 

03/28/2012 
04/10/2010 

07/01/2011 
100   

08/31/2011 


-2 
Begin Closeout Phase

End Closeout Phase
04/11/2011 

07/01/2011 
 

 
07/11/2011 

02/01/2012 
50   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 4 4

Bond Funding Cost
Adopted:
$9,926,000
Current Approved:
$7,556,000
Actual Expenditures:
$7,044,124

Click to view the Final Audit Report

 

Status as of December 31, 2023.