Hageman Road/BNSF Railroad Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City
Zip Code
 
Senate District
32
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  20    20  
MPH Increase in Project Area  10    10  
Peak Period Time Savings (minutes)  11    11  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$17,650 $-3,891 $13,759
Non-bond Funding
Local**
$14,120 $0 $14,120
Private***
$3,530 $0 $3,530
 
Total**** $35,300 $-3,891 $31,409

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,500 $0 $2,500 $10,472 $10,472 $-7,972
Right of Way
$4,500 $0 $4,500 $8,572 $8,572 $-4,072
Construction
$28,300 $-3,891 $24,409 $19,583 $19,583 $4,826
 
Total* $35,300 $-3,891 $31,409 $38,627 $38,627 $-7,218

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/2008 

08/02/2008 
 

 
08/01/2008 

08/02/2008 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/15/2008 

12/30/2009 
 

 
08/15/2008 

12/30/2009 
100   

06/30/2010 


-6 
Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

03/30/2010 
 

 
04/01/2009 

03/30/2010 
100   

08/30/2011 


-17 
Begin Construction Phase

End Construction Phase
06/01/2010 

07/30/2012 
03/28/2012 

 
12/15/2010 

07/30/2012 
80   

07/30/2012 


Begin Closeout Phase

End Closeout Phase
08/01/2012 

10/30/2012 
 

 
08/01/2012 

10/30/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 20 20
MPH Increase in Project Area 10 10
Peak Period Time Savings (minutes) 11 11

Bond Funding Cost
Adopted:
$17,650,000
Current Approved:
$15,293,000
Actual Expenditures:
$13,747,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.