Santa Margarita River Bridge and Double Track

Description: Replace existing single-track bridge with a new double-track bridge

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City
Zip Code
 
Senate District
38
Assembly District 73
Congressional District 49
 
Caltrans District
11
 
 
County/State Route San Diego PS
Postmile Begin/End 222.8 225.3
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
MPH Increase in Project Area  40      
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Mary Estensen 916-654-5982   Mary.Estensen@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$16,206 $-458 $15,748
Non-bond Funding
State/Federal*
$26,494 $0 $26,494
Local**
$0 $1,700 $1,700
 
Total**** $42,700 $1,242 $43,942

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$500 $0 $500 $0 $0 $500
Design(PS&E)
$2,987 $0 $2,987 $987 $987 $2,000
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$39,213 $1,242 $40,455 $38,755 $38,755 $1,700
 
Total* $42,700 $1,242 $43,942 $39,742 $39,742 $4,200

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2005 

10/01/2006 
 

 
10/01/2005 

10/01/2006 
100  10/01/2005 

10/01/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/31/2006 

09/30/2008 
05/20/2010 

05/20/2010 
04/30/2007 

06/30/2009 
100  04/30/2007 

06/30/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2009 

03/31/2011 
08/12/2010 

10/08/2013 
01/18/2010 

05/31/2014 
100  01/18/2010 

06/30/2016 


-25 
Begin Closeout Phase

End Closeout Phase
 

 
10/08/2013 

07/15/2016 
06/01/2014 

06/30/2015 
100  07/01/2016 

07/30/2016 
-25 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
MPH Increase in Project Area 40
System Enhancement

Bond Funding Cost
Adopted:
$16,206,000
Current Approved:
$16,206,000
Actual Expenditures:
$15,747,877

 

Status as of December 31, 2023.