SCRRA Sealed Corridor |
Description: Construction of a the fiber optics element at a number of grade crossings and nearby right of way on the Metrolink system.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo, Los Angeles, Orange, Santa Barbara, San Diego, Ventura |
City | |
Zip Code | |
Senate District |
15, 19, 20, 21, 23, 27, 28, 35, 38, 39 |
Assembly District | 33, 35, 37, 38, 39, 42, 43, 47, 48, 51, 54, 55, 67, 70, 73, 74, 75, 76 |
Congressional District | 23, 24, 27, 30, 33, 36, 37, 38, 39, 40, 44, 46, 48, 49, 50, 51, 53 |
Caltrans District |
05, 07, 11, 12 |
County/State Route | Orange PS |
Postmile Begin/End | 165 207.4 |
County/State Route | San Diego PS |
Postmile Begin/End | 207.4 267.6 |
County/State Route | San Luis Obispo PS |
Postmile Begin/End | 248.5 251.5 |
County/State Route | Santa Barbara PS |
Postmile Begin/End | 251.5 368.6 |
County/State Route | Ventura PS |
Postmile Begin/End | 368.6 442 |
County/State Route | Los Angeles PS |
Postmile Begin/End | 442 165 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Sharon Beasley | 916-657-5206 | Sharon.Beasley@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$3,000 | $-218 | $2,782 | ||||
Non-bond Funding | |||||||
State/Federal* |
$10,754 | $-10,754 | $0 | ||||
Local** |
$491 | $-491 | $0 | ||||
Total**** | $14,245 | $-11,463 | $2,782 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,891 | $-1,891 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$12,354 | $-9,572 | $2,782 | $2,781 | $2,781 | $1 | |
Total* | $14,245 | $-11,463 | $2,782 | $2,781 | $2,781 | $1 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/01/2006 06/30/2007 |
04/10/2008 03/24/2011 |
11/01/2006 12/01/2010 |
100 | 12/01/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 06/01/2008 |
02/14/2008 09/15/2011 |
01/03/2011 06/30/2011 |
100 | 01/03/2010 06/30/2011 |
12 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/30/2008 11/15/2012 |
03/24/2011 03/24/2011 |
11/01/2011 10/31/2012 |
100 | 11/01/2011 02/21/2013 |
0 -4 |
Begin Closeout Phase
End Closeout Phase |
|
03/24/2011 03/24/2011 |
11/01/2012 05/30/2013 |
0 | 11/01/2012 12/31/2013 |
0 -7 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement |
Bond Funding Cost | |
---|---|
Adopted: |
$3,000,000 |
Current Approved: |
$3,000,000 |
Actual Expenditures: |
$2,781,257 |
Status as of December 31, 2023.