Caltrans Logo

SCRRA Sealed Corridor

Description: Construction of a the fiber optics element at a number of grade crossings and nearby right of way on the Metrolink system.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo, Los Angeles, Orange, Santa Barbara, San Diego, Ventura
City
Zip Code
 
Senate District
15, 19, 20, 21, 23, 27, 28, 35, 38, 39
Assembly District 33, 35, 37, 38, 39, 42, 43, 47, 48, 51, 54, 55, 67, 70, 73, 74, 75, 76
Congressional District 23, 24, 27, 30, 33, 36, 37, 38, 39, 40, 44, 46, 48, 49, 50, 51, 53
 
Caltrans District
05, 07, 11, 12
 
 
County/State Route Orange PS
Postmile Begin/End 165 207.4
 
County/State Route San Diego PS
Postmile Begin/End 207.4 267.6
 
County/State Route San Luis Obispo PS
Postmile Begin/End 248.5 251.5
 
County/State Route Santa Barbara PS
Postmile Begin/End 251.5 368.6
 
County/State Route Ventura PS
Postmile Begin/End 368.6 442
 
County/State Route Los Angeles PS
Postmile Begin/End 442 165
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Sharon Beasley 916-657-5206   Sharon.Beasley@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$3,000 $-218 $2,782
Non-bond Funding
State/Federal*
$10,754 $-10,754 $0
Local**
$491 $-491 $0
 
Total**** $14,245 $-11,463 $2,782

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,891 $-1,891 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$12,354 $-9,572 $2,782 $2,781 $2,781 $1
 
Total* $14,245 $-11,463 $2,782 $2,781 $2,781 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2006 

06/30/2007 
04/10/2008 

03/24/2011 
11/01/2006 

12/01/2010 
100   

12/01/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

06/01/2008 
02/14/2008 

09/15/2011 
01/03/2011 

06/30/2011 
100  01/03/2010 

06/30/2011 
12 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/30/2008 

11/15/2012 
03/24/2011 

03/24/2011 
11/01/2011 

10/31/2012 
100  11/01/2011 

02/21/2013 


-4 
Begin Closeout Phase

End Closeout Phase
 

 
03/24/2011 

03/24/2011 
11/01/2012 

05/30/2013 
11/01/2012 

12/31/2013 


-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
$3,000,000
Current Approved:
$3,000,000
Actual Expenditures:
$2,781,257

 

Status as of December 31, 2023.