Emeryville Station and Track Improvements

Description: Extend siding track with associated signal, track and roadway undercrossing improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Emeryville
Zip Code
 
Senate District
09
Assembly District 14, 16
Congressional District 09
 
Caltrans District
04
 
 
County/State Route Alameda CC
Postmile Begin/End 3.5 5.5
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Sharon Beasley 916-657-5206   Sharon.Beasley@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$10,000 $-3,849 $6,151
Non-bond Funding
State/Federal*
$642 $-642 $0
Local**
$0 $225 $225
 
Total**** $10,642 $-4,266 $6,376

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$25 $200 $225 $225 $225 $0
Design(PS&E)
$167 $-167 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$10,450 $-4,299 $6,151 $6,151 $6,151 $0
 
Total* $10,642 $-4,266 $6,376 $6,376 $6,376 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2001 

09/30/2001 
02/14/2008 

02/14/2008 
03/01/2001 

07/30/2006 
100  03/01/2001 

07/30/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2001 

10/31/2001 
02/14/2008 

02/14/2008 
03/01/2001 

10/31/2001 
100  03/01/2001 

10/31/2001 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/31/2008 

08/31/2011 
05/20/2008 

05/20/2008 
06/01/2008 

06/05/2012 
100  06/01/2008 

06/05/2012 


Begin Closeout Phase

End Closeout Phase
09/01/2001 

03/01/2012 
05/20/2008 

05/20/2008 
12/01/2011 

02/21/2012 
25  12/01/2011 

02/29/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$6,250,000
Actual Expenditures:
$6,150,679

 

Status as of December 31, 2023.