Ventura County Sealed Corridor

Description: Enhance safety of grade crossings and Railroad Right of Way

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
07
 
 
County/State Route Ventura PS
Postmile Begin/End
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Bruce Plowman (916) 657-3875   Bruce.Plowman@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$0 $218 $218
Non-bond Funding
State/Federal*
$0 $7,200 $7,200
 
Total**** $0 $7,418 $7,418

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $7,418 $7,418 $6,517 $7,390 $28
 
Total* $0 $7,418 $7,418 $6,517 $7,390 $28

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

08/31/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

08/31/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

01/31/2014 


Begin Construction Phase

End Construction Phase
 

 
 

 
01/15/2015 

10/13/2016 
99  01/15/2015 

10/28/2016 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
10/14/2016 

04/15/2017 
10/28/2016 

04/30/2017 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.