Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Seacliff Siding |
Description: New track siding in Seacliff for more control access for the Pacific Surfliner
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
07 |
County/State Route | Ventura PS |
Postmile Begin/End | 386.4 388 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Betty Miller | 916-654-5739 | betty.miller@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$1,000 | $0 | $1,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,302 | $0 | $2,302 | ||||
Local** |
$250 | $0 | $250 | ||||
Total**** | $3,552 | $0 | $3,552 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$3,552 | $0 | $3,552 | $816 | $816 | $2,735 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$0 | $0 | $0 | $0 | $0 | $0 | |
Total* | $3,552 | $0 | $3,552 | $816 | $816 | $2,735 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2017 06/30/2019 |
|
01/01/2017 06/30/2019 |
37 | 03/31/2021 |
0 -21 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2021 12/31/2023 |
|
01/01/2021 12/31/2023 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2024 09/01/2024 |
|
01/01/2024 09/01/2024 |
50 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,000,000 |
Current Approved: |
$1,000,000 |
Actual Expenditures: |
$297,897 |
Status as of December 31, 2023.