Seacliff Siding

Description: New track siding in Seacliff for more control access for the Pacific Surfliner

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
07
 
 
County/State Route Ventura PS
Postmile Begin/End 386.4 388
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Betty Miller 916-654-5739   betty.miller@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$1,000 $0 $1,000
Non-bond Funding
State/Federal*
$2,302 $0 $2,302
Local**
$250 $0 $250
 
Total**** $3,552 $0 $3,552

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$3,552 $0 $3,552 $816 $816 $2,735
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $0 $0 $0 $0 $0
 
Total* $3,552 $0 $3,552 $816 $816 $2,735

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2017 

06/30/2019 
 

 
01/01/2017 

06/30/2019 
37   

03/31/2021 


-21 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2021 

12/31/2023 
 

 
01/01/2021 

12/31/2023 
 

 


Begin Closeout Phase

End Closeout Phase
01/01/2024 

09/01/2024 
 

 
01/01/2024 

09/01/2024 
50   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
$1,000,000
Current Approved:
$1,000,000
Actual Expenditures:
$297,897

 

Status as of December 31, 2023.