Commerce/Fullerton Triple Track Segment 6

Description: Construct approximately 16 miles of third main track for project consisting of 8 individual segments

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Z-Intercity Rai
City
Zip Code
 
Senate District
24, 25, 26, 30, 33, 34
Assembly District 45, 46, 47, 48, 52, 56, 58, 60, 72
Congressional District 34, 38, 39, 40
 
Caltrans District
07, 12
 
 
County/State Route Z-Intercity Rai PS
Postmile Begin/End 147.5 163.5
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
Increase in Transit Ridership        
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$32,000 $-8 $31,992
Non-bond Funding
 
Total**** $32,000 $-8 $31,992

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$32,000 $-8 $31,992 $31,991 $31,991 $1
 
Total* $32,000 $-8 $31,992 $31,991 $31,991 $1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2002 

11/12/2003 
02/14/2008 

02/14/2008 
01/01/2002 

11/12/2003 
100  01/01/2002 

11/12/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2003 

03/31/2006 
02/14/2008 

02/14/2008 
12/01/2003 

03/31/2006 
100  12/01/2003 

03/31/2006 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2009 

06/30/2014 
02/14/2008 

05/20/2010 
02/27/2009 

06/30/2012 
100  02/01/2009 

06/30/2012 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

12/31/2014 
05/20/2010 

09/20/2012 
07/01/2012 

12/31/2012 
100  07/01/2012 

05/08/2013 


-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Transit Ridership
System Enhancement

Bond Funding Cost
Adopted:
$32,000,000
Current Approved:
$32,000,000
Actual Expenditures:
$31,991,132

 

Status as of December 31, 2023.