Caltrans Logo

New Station Track at LA Union Station

Description: Demolish old tracks and construct two new passenger platfom tracks and a new passenger platform

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code
 
Senate District
22, 24, 25, 26
Assembly District 39, 42, 45, 46, 47, 48, 52
Congressional District 34, 35
 
Caltrans District
07
 
 
County/State Route Los Angeles PS
Postmile Begin/End 0 0.1
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Sharon Beasley 916-657-5206   Sharon.Beasley@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$35,100 $-15,001 $20,099
Non-bond Funding
State/Federal*
$0 $2,746 $2,746
Local**
$3,235 $-2,752 $483
 
Total**** $38,335 $-15,007 $23,328

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,475 $-599 $876 $876 $876 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$36,860 $-14,408 $22,452 $21,653 $23,950 $-1,498
 
Total* $38,335 $-15,007 $23,328 $22,529 $24,826 $-1,498

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

01/31/2007 
 

 
 

01/31/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2006 

10/01/2008 
 

05/20/2010 
11/01/2006 

09/30/2010 
100  11/01/2006 

09/30/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/30/2008 

05/30/2011 
03/24/2011 

05/20/2010 
02/07/2011 

02/28/2015 
100  10/02/2012 

06/30/2015 
-20 

-4 
Begin Closeout Phase

End Closeout Phase
 

 
05/20/2010 

05/20/2010 
03/01/2015 

06/30/2015 
07/01/2015 

12/31/2015 
-4 

-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
$35,100,000
Current Approved:
$21,800,000
Actual Expenditures:
$19,453,245

 

Status as of December 31, 2023.