Kings Park Track and Signal Improvements |
Description: Improve track and signals along SanJoaquin intercity rail line near hanford in Kings County
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings |
City | |
Zip Code | |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 20 |
Caltrans District |
06 |
County/State Route | Kings SJ |
Postmile Begin/End | 949 976 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Sharon Beasley | 916-657-5206 | Sharon.Beasley@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$8,500 | $-5,000 | $3,500 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $15,000 | $15,000 | ||||
Total**** | $8,500 | $10,000 | $18,500 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$8,500 | $10,000 | $18,500 | $18,295 | $18,500 | $0 | |
Total* | $8,500 | $10,000 | $18,500 | $18,295 | $18,500 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/2000 10/31/2002 |
|
09/01/2000 10/31/2002 |
100 | 09/01/2000 10/31/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2000 10/31/2002 |
|
09/01/2000 10/31/2002 |
100 | 09/01/2000 10/31/2002 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/31/2008 08/31/2011 |
08/28/2008 05/20/2010 |
11/25/2008 06/30/2012 |
100 | 11/25/2008 06/30/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2011 03/01/2012 |
05/20/2010 05/20/2010 |
07/01/2012 12/31/2012 |
0 | 07/01/2012 12/31/2012 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement |
Bond Funding Cost | |
---|---|
Adopted: |
$8,500,000 |
Current Approved: |
$3,500,000 |
Actual Expenditures: |
$3,500,000 |
Status as of December 31, 2023.