Kings Park Track and Signal Improvements

Description: Improve track and signals along SanJoaquin intercity rail line near hanford in Kings County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City
Zip Code
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
 
County/State Route Kings SJ
Postmile Begin/End 949 976
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Sharon Beasley 916-657-5206   Sharon.Beasley@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$8,500 $-5,000 $3,500
Non-bond Funding
State/Federal*
$0 $15,000 $15,000
 
Total**** $8,500 $10,000 $18,500

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,500 $10,000 $18,500 $18,295 $18,500 $0
 
Total* $8,500 $10,000 $18,500 $18,295 $18,500 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2000 

10/31/2002 
 

 
09/01/2000 

10/31/2002 
100  09/01/2000 

10/31/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2000 

10/31/2002 
 

 
09/01/2000 

10/31/2002 
100  09/01/2000 

10/31/2002 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/31/2008 

08/31/2011 
08/28/2008 

05/20/2010 
11/25/2008 

06/30/2012 
100  11/25/2008 

06/30/2012 


Begin Closeout Phase

End Closeout Phase
09/01/2011 

03/01/2012 
05/20/2010 

05/20/2010 
07/01/2012 

12/31/2012 
07/01/2012 

12/31/2012 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
$8,500,000
Current Approved:
$3,500,000
Actual Expenditures:
$3,500,000

 

Status as of December 31, 2023.