San Onofre to Pulgas Double Track Phase 1 & 2

Description: Construct 4.2 miles of a new second track

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Camp Pendleton
Zip Code 92055
 
Senate District
38
Assembly District 73, 74
Congressional District 44, 49
 
Caltrans District
11
 
 
County/State Route San Diego PS
Postmile Begin/End 212.3 216.5
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Mary Estensen 916-654-5981   Mary.Estensen@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$30,000 $-598 $29,402
Non-bond Funding
State/Federal*
$0 $7,637 $7,637
Local**
$20,822 $-20,822 $0
 
Total**** $50,822 $-13,783 $37,039

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5,621 $-2,235 $3,386 $3,386 $3,386 $0
Design(PS&E)
$1,393 $3,779 $5,172 $5,172 $5,172 $0
Right of Way
$73 $-73 $0 $0 $0 $0
Construction
$43,736 $-15,255 $28,481 $28,309 $28,309 $172
 
Total* $50,822 $-13,783 $37,039 $36,867 $36,867 $172

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/31/2008 

06/30/2010 
05/20/2010 

03/24/2011 
07/28/2009 

08/30/2011 
100  07/28/2009 

08/30/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2010 

02/28/2011 
09/15/2011 

09/15/2011 
07/28/2009 

12/31/2012 
100  07/28/2009 

12/31/2012 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2011 

04/30/2014 
09/15/2011 

09/15/2011 
04/01/2013 

09/30/2016 
100  09/01/2013 

09/30/2016 
-5 

Begin Closeout Phase

End Closeout Phase
05/01/2014 

10/31/2014 
09/15/2011 

09/25/2011 
04/30/2015 

04/30/2020 
06/30/2017 

12/31/2017 
-26 

28 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.