Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Raymer to Bernson Double Track |
Description: Construct approximately six miles of double track along the Pacific Surfliner Corridor in Ventura County
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Ventura |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
|
County/State Route | Ventura PS |
Postmile Begin/End | 453.1 446.8 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Nick Hernandez | 916-654-0594 | nick.hernandez@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$6,081 | $0 | $6,081 | ||||
Non-bond Funding | |||||||
State/Federal* |
$65,064 | $-2,680 | $62,384 | ||||
Local** |
$391 | $-1 | $390 | ||||
Total**** | $71,536 | $-2,681 | $68,855 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$955 | $999 | $1,954 | $1,846 | $1,846 | $108 | |
Design(PS&E) |
$7,081 | $-1,000 | $6,081 | $6,081 | $6,081 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$63,500 | $-2,680 | $60,820 | $0 | $0 | $60,820 | |
Total* | $71,536 | $-2,681 | $68,855 | $7,927 | $7,927 | $60,928 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2012 11/01/2012 |
03/29/2012 03/29/2012 |
06/30/2012 06/30/2014 |
100 | 06/30/2012 03/31/2014 |
0 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
08/01/2014 12/31/2015 |
99 | 08/01/2014 06/30/2016 |
0 -6 |
Begin Right of Way Phase
End Right of Way Phase |
11/01/2012 06/30/2014 |
03/29/2012 03/29/2012 |
11/01/2012 06/30/2014 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2014 11/01/2016 |
03/29/2012 03/29/2012 |
01/01/2016 12/31/2017 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2016 04/30/2017 |
03/29/2012 03/29/2012 |
01/01/2018 07/31/2018 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.