Raymer to Bernson Double Track

Description: Construct approximately six miles of double track along the Pacific Surfliner Corridor in Ventura County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Ventura
City
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District

 
 
County/State Route Ventura PS
Postmile Begin/End 453.1 446.8
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Nick Hernandez 916-654-0594   nick.hernandez@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$6,081 $0 $6,081
Non-bond Funding
State/Federal*
$65,064 $-2,680 $62,384
Local**
$391 $-1 $390
 
Total**** $71,536 $-2,681 $68,855

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$955 $999 $1,954 $1,846 $1,846 $108
Design(PS&E)
$7,081 $-1,000 $6,081 $6,081 $6,081 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$63,500 $-2,680 $60,820 $0 $0 $60,820
 
Total* $71,536 $-2,681 $68,855 $7,927 $7,927 $60,928

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2012 

11/01/2012 
03/29/2012 

03/29/2012 
06/30/2012 

06/30/2014 
100  06/30/2012 

03/31/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
08/01/2014 

12/31/2015 
99  08/01/2014 

06/30/2016 


-6 
Begin Right of Way Phase

End Right of Way Phase
11/01/2012 

06/30/2014 
03/29/2012 

03/29/2012 
11/01/2012 

06/30/2014 
 

 


Begin Construction Phase

End Construction Phase
07/01/2014 

11/01/2016 
03/29/2012 

03/29/2012 
01/01/2016 

12/31/2017 
 

 


Begin Closeout Phase

End Closeout Phase
11/01/2016 

04/30/2017 
03/29/2012 

03/29/2012 
01/01/2018 

07/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.