Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Van Nuys North Platform |
Description: Project will complete final design of a north platform at the Van Nuys Amtrak Station..
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 91405 |
Senate District |
20 |
Assembly District | 46 |
Congressional District | 29 |
Caltrans District |
07 |
County/State Route | Los Angeles PS |
Postmile Begin/End | 455 455 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
Southern California Regional Rail Authority | Andrew Althorp | 909-392-8421 | AlthorpA@scrra.net | |
Right of Way Phase |
|||||
Construction Phase |
Southern California Regional Rail Authority | Andrew Althorp | 909-392-8421 | AlthorpA@scrra.net | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$0 | $34,919 | $34,919 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $800 | $800 | ||||
Local** |
$0 | $350 | $350 | ||||
Private*** |
$0 | $425 | $425 | ||||
Total**** | $0 | $36,494 | $36,494 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $1,000 | $1,000 | $742 | $742 | $258 | |
Design(PS&E) |
$0 | $3,852 | $3,852 | $3,850 | $3,850 | $2 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$0 | $31,642 | $31,642 | $30,613 | $30,613 | $1,029 | |
Total* | $0 | $36,494 | $36,494 | $35,205 | $35,205 | $1,288 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | 05/18/2012 03/31/2014 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | 03/01/2016 04/30/2017 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
06/30/2021 06/30/2021 |
08/11/2017 09/30/2021 |
100 | 08/11/2017 12/31/2021 |
0 -3 |
Begin Closeout Phase
End Closeout Phase |
|
06/30/2021 06/30/2021 |
10/01/2020 12/31/2021 |
0 | 01/01/2022 08/31/2022 |
-15 -8 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$34,919,000 |
Actual Expenditures: |
$33,921,692 |
Status as of December 31, 2023.