Caltrans Logo

Van Nuys North Platform

Description: Project will complete final design of a north platform at the Van Nuys Amtrak Station..

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 91405
 
Senate District
20
Assembly District 46
Congressional District 29
 
Caltrans District
07
 
 
County/State Route Los Angeles PS
Postmile Begin/End 455 455
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
System Enhancement  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Southern California Regional Rail Authority Andrew Althorp 909-392-8421   AlthorpA@scrra.net
Right of Way Phase
 
Construction Phase
Southern California Regional Rail Authority Andrew Althorp 909-392-8421   AlthorpA@scrra.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$0 $34,919 $34,919
Non-bond Funding
State/Federal*
$0 $800 $800
Local**
$0 $350 $350
Private***
$0 $425 $425
 
Total**** $0 $36,494 $36,494

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $1,000 $1,000 $742 $742 $258
Design(PS&E)
$0 $3,852 $3,852 $3,850 $3,850 $2
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $31,642 $31,642 $30,613 $30,613 $1,029
 
Total* $0 $36,494 $36,494 $35,205 $35,205 $1,288

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  05/18/2012 

03/31/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100  03/01/2016 

04/30/2017 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
06/30/2021 

06/30/2021 
08/11/2017 

09/30/2021 
100  08/11/2017 

12/31/2021 


-3 
Begin Closeout Phase

End Closeout Phase
 

 
06/30/2021 

06/30/2021 
10/01/2020 

12/31/2021 
01/01/2022 

08/31/2022 
-15 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1 1

Bond Funding Cost
Adopted:
$0
Current Approved:
$34,919,000
Actual Expenditures:
$33,921,692

 

Status as of December 31, 2023.