Left Hand Turnout |
Description: Replace a #24 left hand turnout with an #24 equilateral turnout to allow for a 75 mph passenger track speed on the turnout and 90mph on the mainline.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | Oceanside |
Zip Code | 92054 |
Senate District |
36, 39 |
Assembly District | 78, 79 |
Congressional District | 49 |
Caltrans District |
11 |
County/State Route | San Diego PS |
Postmile Begin/End | 209.1 209.1 |
CC = Capital Corridor PS = Pacific Surfliner SJ = San Joaquin |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
MPH Increase in Project Area | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
NORTH COUNTY TRANSIT DISTRICT | Tyler Farrar | 760-966-6580 | TFarrar@nctd.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RAIL |
$1,000 | $0 | $1,000 | ||||
Non-bond Funding | |||||||
Total**** | $1,000 | $0 | $1,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,000 | $0 | $1,000 | $1,000 | $1,000 | $0 | |
Total* | $1,000 | $0 | $1,000 | $1,000 | $1,000 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2017 06/01/2017 |
|
01/01/2017 06/01/2017 |
100 | 01/01/2017 07/31/2017 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/20/2017 03/30/2019 |
|
07/20/2017 03/30/2019 |
100 | 11/01/2017 01/31/2019 |
-3 2 |
Begin Closeout Phase
End Closeout Phase |
04/01/2019 06/30/2019 |
|
04/01/2019 06/30/2019 |
50 | 06/01/2019 06/30/2020 |
-2 -12 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
MPH Increase in Project Area | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,000,000 |
Current Approved: |
$1,000,000 |
Actual Expenditures: |
$1,000,000 |
Status as of December 31, 2023.