Left Hand Turnout

Description: Replace a #24 left hand turnout with an #24 equilateral turnout to allow for a 75 mph passenger track speed on the turnout and 90mph on the mainline.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Oceanside
Zip Code 92054
 
Senate District
36, 39
Assembly District 78, 79
Congressional District 49
 
Caltrans District
11
 
 
County/State Route San Diego PS
Postmile Begin/End 209.1 209.1
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin
Project Benefits
 Benefit Baseline Actual
MPH Increase in Project Area  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
NORTH COUNTY TRANSIT DISTRICT Tyler Farrar 760-966-6580   TFarrar@nctd.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RAIL
$1,000 $0 $1,000
Non-bond Funding
 
Total**** $1,000 $0 $1,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,000 $0 $1,000 $1,000 $1,000 $0
 
Total* $1,000 $0 $1,000 $1,000 $1,000 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2017 

06/01/2017 
 

 
01/01/2017 

06/01/2017 
100  01/01/2017 

07/31/2017 


-2 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
07/20/2017 

03/30/2019 
 

 
07/20/2017 

03/30/2019 
100  11/01/2017 

01/31/2019 
-3 

Begin Closeout Phase

End Closeout Phase
04/01/2019 

06/30/2019 
 

 
04/01/2019 

06/30/2019 
50  06/01/2019 

06/30/2020 
-2 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
MPH Increase in Project Area 1 1

Bond Funding Cost
Adopted:
$1,000,000
Current Approved:
$1,000,000
Actual Expenditures:
$1,000,000

 

Status as of December 31, 2023.