Proposition 1B - Corridor Mobility Improvement Account (CMIA)
Title | County | State Route |
Total Project Cost (x1000) |
Total Bond Funding* (x1000) |
Planned Construction Start |
Planned Construction Finish |
Eastbound I-580 HOV- Hacienda to Greenville
|
Alameda | 580 | $147,749 | $54,341 | 06/01/2008 | 11/01/2014 |
Freeway Performance Initiative - TOS and Ramp Metering Elements
|
Alameda | 680 | $7,860 | $5,740 | 11/01/2012 | 11/01/2014 |
I-580 Westbound HOV Lane - Greenville to Foothill
|
Alameda | 580 | $160,377 | $82,341 | 10/29/2012 | 11/30/2016 |
I-580/Isabel Interchange
|
Alameda | 580 | $123,487 | $45,127 | 06/01/2009 | 03/01/2012 |
I-880 Southbound HOV Lane Extension - Hegenberger to Marina Blvd
|
Alameda | 880 | $104,369 | $82,611 | 08/01/2012 | 02/01/2016 |
Route 24 Caldecott Tunnel Fourth Bore
|
Alameda | 24 | $404,583 | $84,482 | 11/01/2009 | 05/01/2014 |
Route 84 Expressway Widening - Segment 1 & 2
|
Alameda | 84 | $138,467 | $16,057 | 11/30/2011 | 10/01/2015 |
SR 32 Widen Phase 1
|
Butte | 32 | $9,925 | $3,425 | 06/30/2012 | 11/30/2013 |
State Route 4 Angels Camp Bypass
|
Calaveras | 4 | $60,688 | $3,574 | 09/01/2007 | 09/01/2010 |
I-80 Integrated Corridor Mobility Project
|
Contra Costa, Alameda | 80 | $57,600 | $44,238 | 04/01/2011 | 05/22/2017 |
US 50 HOV Lanes - Corridor Project
|
El Dorado | 50 | $54,888 | $26,160 | 12/01/2008 | 10/01/2013 |
US Route 50 HOV Lanes Phase 0
|
El Dorado | 50 | $19,200 | $15,500 | 07/17/2012 | 12/31/2013 |
Western Placerville Interchange Phase 1A - Westbound US 50 On Ramp
|
El Dorado | 50 | $9,145 | $6,000 | 11/05/2012 | 11/30/2014 |
Route 46 Expressway - Segment 3
|
Kern | 46 | $73,024 | $30,375 | 07/01/2010 | 07/26/2014 |
Route 198 Expressway
|
Kings | 198 | $94,274 | $44,272 | 10/01/2009 | 02/01/2012 |
Gerald Desmond Bridge Replacement Project
|
Los Angeles | 710 | $1,336,061 | $153,657 | ||
I-405 Carpool Lane I-10 to US 101 (Northbound)
|
Los Angeles | 405 | $1,137,700 | $730,000 | 04/23/2009 | 03/01/2017 |
Interstate 5 Carpool Lane from Rte 134 to Rte 170
|
Los Angeles | 5 | $752,069 | $64,713 | 10/14/2010 | 12/31/2019 |
Interstate 5 Carpool and Mixed Flow Lane from Orange County Line to Interstate 605
|
Los Angeles | 5 | $1,483,611 | $315,011 | 11/28/2011 | 09/13/2019 |
Westbound I-580 to Northbound 101 Connector Improvements
|
Marin | 580, 101 | $16,985 | $16,985 | 11/04/2009 | 03/31/2011 |
Highway 101 Marin-Sonoma Narrows (MSN) Project Segment A (modified)
|
Marin, Sonoma | 101 | $326,422 | $179,346 | 12/01/2010 | 06/01/2015 |
Salinas Road Interchange
|
Monterey | 1 | $31,691 | $18,568 | 05/01/2009 | 07/01/2011 |
San Juan Road Interchange
|
Monterey | 101 | $91,150 | $30,825 | 09/27/2012 | 04/28/2016 |
SR 12 Jameson Canyon - Phase 1
|
Napa | 12 | $120,080 | $54,867 | 09/01/2010 | 03/15/2013 |
Route 49 La Barr Meadows Widening
|
Nevada | 49 | $30,019 | $8,225 | 06/01/2010 | 12/01/2014 |
Add one lane EB SR-91 from SR-241/SR-91 to SR-71/SR-91
|
Orange | 91 | $60,759 | $0 | 08/01/2009 | 09/01/2011 |
Reconstruct I-5 / SR-74 Interchange
|
Orange | 74 | $77,211 | $24,109 | 06/30/2012 | 11/01/2016 |
SR-22/I-405/I-605 HOV Connector with Intelligent Transportation System (ITS) Elements
|
Orange | 22 | $289,103 | $135,430 | 02/01/2010 | 05/01/2014 |
Widen EB and WB SR-91 from East of SR-55 connector (Lakeview Av) to East of Weir Canyon Road
|
Orange | 91 | $77,302 | $54,045 | 12/01/2011 | 12/01/2014 |
Widen NB from 0.3 mile south of Katella Ave to 0.3 mile north of Lincoln Avenue
|
Orange | 57 | $34,428 | $24,127 | 08/01/2011 | 03/01/2015 |
Widen NB from 0.4 mile north of SR-91 to 0.1 mile north of Lambert Road
|
Orange | 57 | $102,006 | $80,763 | 10/01/2010 | 07/01/2014 |
Widen Ramp For Deceleration Lane
|
Orange | 405 | $3,058 | $2,238 | 12/01/2012 | 07/01/2014 |
Lincoln Bypass
|
Placer | 65 | $315,302 | $68,934 | 02/01/2009 | 12/15/2014 |
Pla 80 HOV Phase 2
|
Placer | 80 | $47,286 | $8,193 | 05/01/2008 | 10/01/2010 |
Pla 80 HOV Phase 3
|
Placer | 80 | $48,993 | $22,604 | 05/01/2009 | 01/01/2011 |
Add one mixed flow lane in each direction
|
Riverside | 215 | $29,228 | $25,605 | 12/01/2010 | 12/01/2013 |
HOV Lane Gap closure
|
Riverside | 91 | $253,625 | $120,191 | 02/10/2012 | 11/30/2016 |
I-215 Widening/Scott Rd to Nuevo Rd
|
Riverside | 215 | $123,502 | $38,779 | 10/10/2012 | 12/31/2015 |
Highway 50 Bus/Carpool Lanes & Community enhancements
|
Sacramento | 50 | $96,581 | $47,611 | 01/01/2010 | 01/01/2013 |
I-80 Across the Top Bus/Carpool and Auxiliary Lane
|
Sacramento | 80 | $136,035 | $53,537 | 07/29/2011 | 12/30/2016 |
Watt Ave @ Route 50 Interchange Improvements
|
Sacramento | 50 | $38,319 | $12,109 | 08/21/2012 | 11/30/2014 |
White Rock Road from Grant Line to Prairie City
|
Sacramento | 50 | $16,322 | $12,822 | 04/30/2012 | 12/31/2013 |
I-10 Tippecanoe Ave Interchange Improvements (Phase 1)
|
San Bernardino | 10 | $18,620 | $10,000 | 07/11/2012 | 07/11/2013 |
I-10 Westbound Mixed flow lane addition
|
San Bernardino | 10 | $30,760 | $14,074 | 11/01/2010 | 05/01/2012 |
I-15 Widening and Devore Interchange Reconstruction
|
San Bernardino | 15, 215 | $325,365 | $53,743 | 11/15/2012 | 03/25/2016 |
I-15/Duncan Canyon Road Interchange
|
San Bernardino | 15 | $35,274 | $12,000 | 08/14/2012 | 11/30/2016 |
I-215 Newport Avenue Overcrossing (Combined with San Bernardino 215R, shown for record only)
|
San Bernardino | 215 | $0 | $0 | 12/03/2012 | 08/25/2015 |
Interstate 215 North Segment 5-HOV and Mixed Flow Lane Addition (Combined with San Bernardino 210a)
|
San Bernardino | 215 | $0 | $0 | 08/15/2009 | 02/01/2013 |
Interstate 215 North Segments 1 & 2 - HOV and Mixed Flow Lane Addition
|
San Bernardino | 215 | $347,777 | $49,120 | 09/15/2009 | 09/05/2013 |
Route 15 Ranchero Road Interchange Construction
|
San Bernardino | 15 | $63,923 | $28,264 | 08/01/2012 | 08/01/2014 |
Route 15/La Mesa Road/Nisquali Road Interchange
|
San Bernardino | 15 | $82,912 | $16,206 | 11/30/2011 | 12/01/2013 |
State Route 210/215 Connectors
|
San Bernardino | 210, 215 | $118,272 | $61,414 | 08/01/2009 | 02/01/2013 |
Widen exit ramps and add auxiliary lanes @ Cherry, Citrus & Cedar Ave Interchanges
|
San Bernardino | 10 | $19,409 | $10,910 | 10/12/2010 | 12/20/2012 |
I-215 HOV Bi County Gap Closure Project
|
San Bernardino, Riverside | 215 | $205,061 | $18,357 | 08/31/2012 | 08/29/2014 |
I-15 Mira Mesa / Scripps Ranch Direct Access Ramp
|
San Diego | 15 | $68,159 | $25,802 | 09/21/2011 | 01/04/2015 |
I-5 North Coast Corridor - Stage 1A
|
San Diego | 5 | $133,110 | $24,500 | 08/15/2007 | 02/13/2015 |
I-805 HOV/Managed Lanes-South (Palomar to SR54)
|
San Diego | 805 | $55,432 | $37,978 | 04/30/2012 | 07/30/2014 |
I-805 HOV/Managed Lanes-South (SR54 to SR94)
|
San Diego | 805 | $36,501 | $18,785 | 03/30/2012 | 07/30/2014 |
I-805/HOV Managed Lanes-N
|
San Diego | 805 | $123,028 | $40,638 | 01/13/2012 | 03/15/2015 |
Managed Lanes South Segment
|
San Diego | 15 | $331,081 | $275,596 | 02/25/2008 | 04/15/2012 |
SR 76 / I-15 Interchange Improvement
|
San Diego | 15 | $36,889 | $29,387 | 08/01/2012 | 01/01/2015 |
I-205 auxiliary lanes
|
San Joaquin | 205 | $22,009 | $9,070 | 10/01/2010 | 04/01/2013 |
North Stockton HOV Widening
|
San Joaquin | 5 | $128,578 | $42,470 | 02/01/2011 | 12/30/2014 |
Route 46 Corridor Improvements (Whitley 1)
|
San Luis Obispo | 46 | $79,054 | $49,778 | 08/01/2010 | 08/01/2013 |
Route 46 Corridor Improvements (Whitley 2A)
|
San Luis Obispo | 46 | $55,559 | $45,088 | 08/08/2012 | 09/08/2015 |
Santa Maria River Bridge Widening
|
San Luis Obispo | 101 | $47,857 | $31,174 | 01/15/2011 | 04/01/2014 |
Widen US 101 and add Auxiliary Lanes from Marsh Rd to Embarcadero Rd
|
San Mateo | 101 | $62,007 | $26,102 | 01/03/2011 | 11/01/2013 |
Union Valley Parkway Interchange
|
Santa Barbara | 101 | $17,618 | $4,442 | 08/10/2012 | 12/31/2013 |
I-880 Widening ( SR 237 to US 101)
|
Santa Clara | 880 | $61,802 | $39,842 | 06/01/2011 | 07/01/2013 |
I-880/Stevens Creek Interchange Improvements
|
Santa Clara | 880, 280 | $62,097 | $39,231 | 09/01/2012 | 12/01/2014 |
US 101 Aux Lanes - SR 85 to Embarcadero Rd
|
Santa Clara | 101 | $73,199 | $55,871 | 06/01/2011 | 08/01/2013 |
US 101 Improvements (I-280 to Yerba Buena Rd)
|
Santa Clara | 101 | $49,611 | $16,636 | 09/01/2010 | 06/01/2013 |
US 101/Capitol Expressway-Yerba Buena Interchange
|
Santa Clara | 101 | $33,812 | $22,217 | 08/15/2012 | 11/30/2014 |
Highway 1 Soquel to Morrissey Auxiliary Lanes
|
Santa Cruz | 1 | $21,085 | $13,783 | 11/01/2011 | 11/01/2013 |
Cottonwood Hills Truck Climbing Lane
|
Shasta | 5 | $16,315 | $13,496 | 05/01/2010 | 12/01/2011 |
I-5/Deschutes Road NB Off-Ramp
|
Shasta | 5 | $7,275 | $6,000 | 06/05/2012 | 12/15/2012 |
South Redding I-5 6-lane
|
Shasta | 5 | $22,658 | $20,903 | 06/17/2011 | 11/15/2012 |
Freeway Performance Initiative - TOS and Ramp Meter
|
Solano | 80 | $74,984 | $36,057 | 09/01/2012 | 10/01/2014 |
I-80 HOV Lanes, Fairfield (I-80/I-680/12 to Putah Creek)
|
Solano | 80 | $79,638 | $24,965 | 05/01/2008 | 09/01/2011 |
Central B - Sonoma Highway 101 HOV Lane Widening
|
Sonoma | 101 | $17,321 | $15,000 | 12/01/2010 | 12/31/2012 |
Central Phase A - US101 HOV Lanes from Railroad Ave to Rohnert Park Exp
|
Sonoma | 101 | $92,761 | $17,359 | 07/01/2009 | 12/01/2011 |
North B - Sonoma Highway 101 Airport Interchange
|
Sonoma | 101 | $52,360 | $22,242 | 10/01/2012 | 10/31/2014 |
US 101 HOV Lanes - North Phase A (from Steele Lane to Windsor River Road)
|
Sonoma | 101 | $120,260 | $69,860 | 09/01/2008 | 01/01/2011 |
US 101 HOV Lanes - Wilfred
|
Sonoma | 101 | $79,367 | $29,280 | 03/01/2009 | 12/01/2013 |
Route 219 Expressway Phase 1 (SR-99 to Morrow Road)
|
Stanislaus | 219 | $44,353 | $8,617 | 11/01/2007 | 08/01/2009 |
Route 219 Expressway Phase2 (Morrow Road to Route 108)
|
Stanislaus | 219 | $42,662 | $13,241 | 05/30/2012 | 05/30/2014 |
Plaza Drive Interchange/Auxiliary Lanes
|
Tulare | 198 | $27,266 | $21,187 | 11/30/2011 | 06/30/2013 |
E. Sonora Bypass Stage II
|
Tuolumne | 108 | $53,392 | $25,577 | 03/01/2012 | 03/10/2014 |
HOV Lanes, Mussel Shoals to Casitas Pass Road
|
Ventura | 101 | $101,163 | $81,293 | 05/12/2011 | 08/25/2014 |
Total | $12,118,121 | $4,375,093 |
* Represents total planned project budget not expenditures