Proposition 1B - Intercity Rail Improvement

Title County State
Route
Total Project
Cost
(x1000)
Total
Bond
Funding*
(x1000)
Planned
Construction
Start
Planned
Construction
Finish
Emeryville Station and Track Improvements
Alameda CC $6,376 $6,151 Jun 01, 2008 Jun 05, 2012
Wireless Network for Northern California IPR Fleet
Alameda CC $2,927 $2,927 Feb 01, 2011 Jun 30, 2015
Oakley to Port Chicago Double Track (Segment 3)
Contra Costa SJ $23,150 $23,150 Sep 01, 2012 Feb 28, 2017
Kings Park Track and Signal Improvements
Kings SJ $18,500 $3,500 Nov 25, 2008 Jun 30, 2012
Capitalized Maintenance So.Cal. Signal & Track Modernization
Los Angeles PS $32,916 $2,000 Dec 01, 2020 Jun 30, 2023
New Station Track at LA Union Station
Los Angeles PS $23,328 $20,099 Feb 07, 2011 Feb 28, 2015
Van Nuys North Platform
Los Angeles PS $36,494 $34,919 Aug 11, 2017 Sep 30, 2021
Passing Siding, Laguna Niguel - San Juan Capistrano
Orange PS $34,445 $2,000 Mar 30, 2019 Mar 30, 2021
Wayside Power and Storage
Placer $1,200 $900 Jul 01, 2016 Dec 01, 2017
Sacramento to Roseville Third Mainline Track
Sacramento CC $214,512 $18,251 Nov 01, 2023 Mar 31, 2028
Left Hand Turnout
San Diego PS $1,000 $1,000 Jul 20, 2017 Mar 30, 2019
San Onofre to Pulgas Double Track Phase 1 & 2
San Diego PS $37,039 $29,402 Apr 01, 2013 Sep 30, 2016
Santa Margarita River Bridge and Double Track
San Diego PS $43,942 $15,748 Jan 18, 2010 May 31, 2014
Los Alamos Creek Bridge (Narlon) Replacement
Santa Barbara PS $22,000 $15,526 Aug 01, 2020 Dec 31, 2022
Bahia Benicia Crossover and Track Improvement Project
Solano CC $6,385 $3,445 Feb 01, 2010 Jun 30, 2013
Capitol Corridor Track, Bridge and Signal Upgrade Project
Various CC $1,305 $1,305 May 31, 2014 May 31, 2017
Raymer to Bernson Double Track
Ventura PS $68,855 $6,081 Jan 01, 2016 Dec 31, 2017
Seacliff Siding
Ventura PS $3,552 $1,000 Jan 01, 2021 Dec 31, 2023
Ventura County Sealed Corridor
Ventura PS $7,418 $218 Jan 15, 2015 Oct 13, 2016
SCRRA Sealed Corridor
Ventura, Santa Barbara, Los Angeles, Orange, San Diego PS $2,782 $2,782 Nov 01, 2011 Oct 31, 2012
Commerce/Fullerton Triple Track Segment 6
Z-Intercity Rai PS $31,992 $31,992 Feb 27, 2009 Jun 30, 2012
Interim San Luis Obispo Layover Facility Expansion
Z-Intercity Rai PS $300 $300 Nov 01, 2021 Jan 31, 2022
Procurement of Locomotives and Railcars
Z-Intercity Rai $316,582 $150,000 Oct 01, 2012 Dec 31, 2025
Total $937,000 $372,696    
CC = Capital Corridor
PS = Pacific Surfliner
SJ = San Joaquin

* Represent total bond funds planned